Forklift charging station in Duncan SC
Rudin Electric completed an electric charger installation for forklifts in Duncan, SC, following a careful plan that prioritized safety, durability, and code compliance. The project focused on a warehouse charging area where accessibility, power requirements, and protection for wiring were important considerations.
We began with a site assessment to determine the best mounting location and to confirm the charger’s power needs based on the forklifts in use. During this step we reviewed proximity to the charging zone, ease of access for operators, and any local permitting or inspection requirements in Duncan, SC. Establishing the correct electrical load and route for the conduit helped prevent issues during the rest of the installation.
Material selection was a key part of the project. The team chose a commercial-grade electric charger suited for industrial forklift charging, and EMT conduit for the wiring runs along the concrete wall. EMT conduit was selected because it provides solid mechanical protection in busy warehouse environments and keeps conductors shielded from physical damage.
Preparing the installation area included clearing the wall space where the charger and conduit would be mounted and marking precise locations for anchors, conduit runs, and the charging unit. We made sure the concrete wall was accessible and free of debris to allow straight, level conduit runs and secure fastenings.
Installation of the EMT conduit required careful measurement and cutting to fit the marked pathway. Conduit fittings were used to create continuous runs, and holes were drilled into the concrete for anchor bolts. The conduit was fastened to the wall with anchors spaced to provide adequate support along the length of each run, keeping everything stable and professional in appearance.
High-quality conductors were selected to handle the charger’s electrical load. The wiring was pulled through the EMT conduit, with attention to maintaining clean, code-compliant connections. Wire connectors and secure wrapping were used where required to protect terminations and reduce the chance of loose connections or interference.
With wiring in place, the charging unit was mounted to the wall at a height that allowed easy access for operators. The supply conductors were terminated at the charger following the manufacturer’s instructions and verified for proper polarity and tightness.
Testing and final inspection were completed after installation. The charger was tested to confirm it operated correctly under load, and all connections were inspected for security. Where required by local code, a licensed electrician or inspector reviewed the work to ensure compliance with regulations in Duncan, SC.
The result is a durable, code-conscious charging installation that protects wiring with EMT conduit and uses quality wiring sized for the load. Rudin Electric delivered a solution that supports reliable forklift charging, improves safety in the charging area, and helps prolong the life of the electrical system through careful planning and professional execution.
Service provided: EV Charger InstallationBudget: 2000
Location: Duncan, SC